New Housing Project, Stratford-upon-Avon
A housing project needed a faster-drying screed over a Lewis metal decking system on a first floor, hitting a strict six-week deadline. XTR FD was specified across 150 m² for its compatibility with Lewis Deck. The floor was dry and ready for coverings after just 28 days.
Location
Stratford-upon-Avon
Date
December 2019
Product
XTR FD E2C
Installer
CV Pumping
Application
Housing — first-floor Lewis Deck
The challenge
A faster drying screed was required to be used over a Lewis metal decking system on a first floor. Lewis Decking is a lightweight flooring system that has good strength, sound and fire ratings ideal for first floors; giving a thin section, lightweight floor.
The solution
XTR FD is compatible with the Lewis Deck system and provided reassurance to the customer that their 6-week deadline would be achieved comfortably.
Results
The floor was dry and ready for floor coverings after 28 days.