New Luxury Development, Morpeth

A luxury development of two £1m houses needed a quick turnaround so the buyers could move in early. ECO fast-drying screed was installed at 40 mm over Kingspan insulation with water-fed UFH across 240 m². Drying times were halved, letting floor coverings go down a month early and cutting the overall build time.

Location
Northumberland
Date
March 2020
Product
ECO FD — 40 mm
Installer
EDS Floors
Application
Luxury development of two £1m houses

The challenge

A quick turnaround to complete the house enabling the buyer to move in sooner than the expected 'moving in' date.

The solution

Gyvlon ECO FD which dries twice as fast as standard flowing and traditional screeds.

Results

Drying times reduced by at least a half meaning that their floor covering could be laid a month early; reducing the build time.