Treforest Industrial Estate Renovation, Cardiff
The client wanted a thin, level, jointless floor across a former BBC building being converted to offices and a workshop. Ready-mix EXCELIO screed was bonded at an average depth of 20 mm across 850 m². It was poured and finished in one morning, with foot traffic the next day and a major cut in embodied carbon.
The challenge
The client required a thin level floor for this former BBC building as its use was being changed to offices and a workshop and they didn't want any joints.
The solution
Ready-mix Gyvlon Excelio bonded at an average depth of 20 mm.
Results
This resulted in a fantastic looking floor, all poured and finished in one morning, enabling foot traffic the following day.
No site mixing, and no bag packaging to dispose of — greatly reducing the embodied carbon content of the floor compared to bagged / cementitious products.